3-way match tolerance and lane-routing policy builder
8 controls that show how 10 invoice exception types go to the 3 lanes, and a plain AP control policy to copy.
Cutover planner · Matchdesk
This planner is for a CFO, a finance manager or an IT and ERP manager at a factory in Singapore or Malaysia. Enter 7 figures: your ERP export route, the deployment mode, the supplier invoices of 1 month, the active suppliers, the share of scanned delivery orders (DOs), the share of foreign-currency invoices and the size of a sample of past invoices. The planner gives a 4-stage schedule for a shadow run and a parallel cutover, 2 readiness checklists and a sign-off plan that you can copy. Every stage reads CSV or Excel export files only. No stage writes to your ERP. The planner runs in your browser. It saves nothing and sends nothing.
Choose an answer in the 2 lists and type a number in the 5 number fields. The schedule and the 2 checklists change as you type.
Operational planning template only — the working days come from your own figures and the fixed planning values of this page. They are not a measured result, a quote or a delivery promise. WorkflowLab agrees the real scope and the dates with you in the Workflow Diagnostic.
The table shows the 4 stages for the figures in the fields. Each row has the working days, the calendar weeks, the owner, the exit gate and the ERP writes. A stage does not start before the exit gate of the stage before it is signed.
| Stage | Working days | Calendar weeks | Owner | Exit gate | ERP writes |
|---|---|---|---|---|---|
| Stage 1: Read-only ERP export and column check | 3 working days | Week 1 | IT or ERP administrator, with Finance | The 3 export files open as CSV or Excel, and each file holds the columns in the IT checklist. | 0. Your team makes the export files. Matchdesk reads the files only. |
| Stage 2: Blind historical shadow run | 4 working days | Weeks 1 to 2 | Finance or AP, with WorkflowLab | Finance writes its own result for each of the 30 sample invoices before it sees the Matchdesk result. A person explains each difference between the 2 results in writing. | 0. The run reads export files and scans of past invoices. Nothing is posted. |
| Stage 3: Live parallel run with Finance dual-check | 9 working days | Weeks 2 to 4 | Finance or AP, with Receiving or the warehouse | For 9 working days, Finance checks each new invoice in its usual way and in Matchdesk. Finance and the process owner sign a go, wait or stop decision. | 0. Your team keys and posts each invoice in the ERP in its usual way. |
| Stage 4: Steady-state daily triage | Each working day: about 18.2 invoices | From week 5 | AP and buyers. A person approves each payment. | No end date. Each working day, a buyer clears the 3 lanes: Auto-Matched, 1-Click Confirm and Hard Stop. | 0. Matchdesk never writes to the ERP. |
The calendar weeks include 3 working days for 1 month-end close. No stage starts or ends in those days, so your close goes on as usual.
Each line shows the arithmetic for the figures in the fields. You can check each line by hand.
Stage 1: 2 + 0 + 0 + 1 = 3 working days. The 4 parts are the base, an ERP that is not in the list, a cloud sandbox and the currency column check.
Stage 2: 30 ÷ 20 = 1.5, so the blind review takes 2 working days. 2 + 1 + 1 = 4 working days. The 3 parts are the review, the comparison and the scan of paper DOs.
Stage 3: 5 × 30 = 150 invoices for the parallel run. 150 × 22 ÷ 400 = 8.25. A part of a day counts as 1 day, so the run takes 9 working days.
Total: 3 + 4 + 9 + 3 = 19 working days. The last part is the pause for 1 month-end close. 19 ÷ 5 = 3.8, so the plan takes 4 calendar weeks.
Stage 4: 400 ÷ 22 = 18.2 invoices each working day.
Scanned or paper DOs: 40% × 30 = 12 sample invoices.
Foreign currency: 25% × 30 = 8 sample invoices.
The 2 lists follow the figures in the fields: the ERP export route, the deployment mode, the scanned DO share and the foreign-currency share.
The table lists each input and what the plan does with it.
| Input | Value | What the plan does |
|---|---|---|
| ERP export route | An ERP in the list | Stage 1 has no extra day. The IT checklist names the 3 export files. |
| ERP export route | Other ERP (CSV or Excel export) | Stage 1 has 1 more day to write down the column names. |
| Deployment mode | On-premise office PC (local) | Stage 1 has no extra day. IT prepares 1 Windows PC or server. |
| Deployment mode | Private cloud sandbox | Stage 1 has 1 more day. IT prepares 1 Windows server in your own private cloud account. |
| Scanned or paper DO share | 0% | Stage 2 has no scan day, and the IT checklist has no scan item. |
| Scanned or paper DO share | Above 0% | Stage 2 has 1 more day to find and scan the paper DOs at 200 DPI or more. |
| Foreign-currency invoice share | 0% | Stage 1 has no currency day, and the Finance checklist has no foreign-currency item. |
| Foreign-currency invoice share | Above 0% | Stage 1 has 1 more day to check the currency column. The Finance checklist states the PO-currency rule. |
| Blind historical sample batch | 10 to 200 invoices | Finance reviews 20 sample invoices in 1 working day. The parallel run covers 5 times the sample. |
| Supplier invoices each month | 1 to 100,000 | A low volume makes the parallel run longer, up to 22 working days. A high volume makes it shorter, down to 5 working days. |
Example only. The 3 columns use example figures. They are not customers, and they are not a quote for your company.
| Item | Example 1: the start values | Example 2: SAP Business One in a cloud sandbox | Example 3: a low-volume site with an ERP that is not in the list |
|---|---|---|---|
| ERP export route | Epicor | SAP Business One | Other ERP (CSV or Excel export) |
| Deployment mode | On-premise office PC (local) | Private cloud sandbox | On-premise office PC (local) |
| Supplier invoices each month | 400 | 1,200 | 60 |
| Blind historical sample batch | 30 invoices | 50 invoices | 20 invoices |
| Sample mix | 12 with a scanned or paper DO, 8 in a foreign currency | 30 with a scanned or paper DO, 0 in a foreign currency | 0 with a scanned or paper DO, 10 in a foreign currency |
| Stage 1 | 3 working days | 3 working days | 4 working days |
| Stage 2 | 4 working days | 5 working days | 2 working days |
| Stage 3 | 9 working days | 5 working days | 22 working days |
| Month-end close pause | 3 working days | 3 working days | 3 working days |
| Total | 3 + 4 + 9 + 3 = 19 working days | 3 + 5 + 5 + 3 = 16 working days | 4 + 2 + 22 + 3 = 31 working days |
| Calendar weeks | 4 | 4 | 7 |
| Stage 4 starts | Week 5 | Week 5 | Week 8 |
| ERP writes | 0 | 0 | 0 |
In example 2, the site matches 1,200 invoices each month. 5 × 50 = 250 invoices pass in less than 5 working days, so the parallel run takes the shortest time: 5 working days.
In example 3, the site matches 60 invoices each month. 5 × 20 = 100 invoices need more than 1 month, so the parallel run takes the longest time: 22 working days.
A plan is not a measurement. The Workflow Diagnostic checks the export from your ERP and your own documents, and gives you a written go, wait or do-not-build decision.
8 controls that show how 10 invoice exception types go to the 3 lanes, and a plain AP control policy to copy.
The invoice exceptions of 1 month in 5 buckets, and the AP hours that they cost.
8 questions that name Matchdesk, a Custom Ops Desk or Prep first.
Three-way invoice matching software for mid-size factories and manufacturers in Singapore and Malaysia. The page lists every check and the 3 lanes.
A guide to where each part of Matchdesk runs, with the cloud reader and the local reader.
A guide to paper DOs, stamps, handwritten changes and invoices that wait for paper.
A guide to the currency rule. Matchdesk uses no exchange rate.
The Workflow Diagnostic costs S$1,000–1,500 for half a day. The fee is credited if the pilot starts within 30 days.
The list of the 7 WorkflowLab browser tools.
A shadow run checks invoices with the new tool beside your usual process. Your team pays and posts each invoice in its usual way. The shadow result is a second answer that you compare with your own answer. Nothing in the ERP changes.
No. Each stage of this plan reads CSV or Excel export files that your team makes. The number of ERP writes in each stage is 0. Matchdesk never writes to the ERP.
The list has Epicor, SAP Business One, NetSuite, AutoCount or Xero, and Other ERP. Each route in this plan is a read-only CSV or Excel export of the PO lines, the goods-receipt lines and the supplier list. This page names no live or certified ERP connector.
Finance writes its own result for each sample invoice before it sees the Matchdesk result. If Finance sees the Matchdesk result first, the 2 results are not independent. A person then explains each difference in writing.
No stage writes to the ERP, so the close works as usual. The plan also holds 3 working days for 1 month-end close. No stage starts or ends in those days.
Matchdesk compares each invoice with its PO in the PO currency. It uses no exchange rate, converts no amount and does not check a printed rate. Finance checks the rate and the amount in your home currency in its own process.
No. The working days come from your own figures and the fixed planning values of this page. They are not a measured result, a quote or a delivery promise. WorkflowLab agrees the real scope and the dates with you in the Workflow Diagnostic.
No. The planner runs in your browser. It saves nothing and sends nothing. The copy button puts the plan on your own clipboard.
Copy the sign-off plan and give it to your Finance lead and your IT or ERP administrator. To check the export from your ERP and your own documents, start with the Workflow Diagnostic. The first conversation needs no confidential files.
Operational planning template only — the working days come from your own figures and the fixed planning values of this page. They are not a measured result, a quote or a delivery promise. WorkflowLab agrees the real scope and the dates with you in the Workflow Diagnostic.