This guide is for a small construction or mechanical and electrical (M&E) subcontractor in Singapore, with fewer than 10 office staff. A Custom Ops Desk is one private browser page or one Excel workbook that WorkflowLab builds around one job. An example is the monthly progress claim. The desk holds the contract items, the claim history and the retention sum, and it does the arithmetic. It covers one job first. It does not decide a claim, and it does not give contract advice.

In short

  • A Custom Ops Desk is for a small Singapore company: fewer than 10 staff and less than S$10M revenue.
  • A progress claim is cumulative: each claim builds on the last one. One wrong figure carries into every later claim.
  • The retention sum is money that you earned and do not yet hold. A desk would show the retention sum for each contract and its release dates.
  • The site delivery order (DO) log is the proof that materials reached the site. A desk would link each DO to a contract.
  • The desk does the arithmetic and the matching. A person makes each decision.
  • There is no public price list. You get one written scope with one fixed price before any build starts.
  • WorkflowLab has no demo for a subcontractor. This guide describes what a desk for this work would hold.

How the work runs today

A small subcontractor often runs 3 to 10 contracts with 1 quantity surveyor or 1 admin. If these 4 points describe your company, a desk can fit.

Each contract has its own claim spreadsheet.

The formulas differ from file to file. Last month's file is the template for this month.

Site DOs are photos in a chat group.

The paper is in the site office or the lorry. Nobody has one list for each contract.

Retention is a number in old claims.

To know the total that customers hold, a person opens every file.

The claim date is fixed.

The contract sets the day. The admin builds each claim in the last 2 days before it.

The risk is not the tools. The risk is that a cumulative figure is copied by hand each month, and that money held as retention has no list.

Four jobs that can be the first job

The table shows what a desk for each job would hold. The written scope names the real fields.

Candidate jobWhat a desk for this job would holdWhat the person decides
Monthly progress claimThe contract items, the percentage done for each item, the earlier claims and the amount of this claim.The percentage done for each item, and what to claim.
Variation order (VO) listOne line for each VO: the instruction, the amount, and whether the customer has approved it.Whether to claim a VO now, and what to follow up.
Site DO logOne line for each delivery: contract, DO number, material, quantity delivered, quantity accepted and who signed.Whether a delivery is complete, and whom to ask about a shortage.
Retention sum listThe retention sum that each customer holds, the limit, and the dates when your contract says it is due.When to ask for release, and whom to ask.

For the payments that come in against each claim, read the bank remittance to Excel SOA guide. A company that also runs maintenance contracts can read the ACMV and M&E maintenance guide.

How to pick the first job

  1. Write the jobs on one page

    Add any monthly job that is not in the table.

  2. Count the hours

    Note the hours each job takes in 1 normal month.

  3. Mark the errors

    Mark each claim that the customer sent back for an arithmetic error.

  4. Name one job

    Choose the job that costs most. That job is the first scope.

  5. Date the others

    Put the other jobs on a dated list.

To turn the hours into an estimate, use the Custom Ops Desk payback calculator. The result is an illustrative estimate from your own figures.

Example: one progress claim with retention

Sample data. Example only. Example M&E Works (sample company) has a subcontract with Customer B (sample) for electrical work. The contract sum is S$180,000.00 before GST. The sample contract holds 10% of each claim as retention, up to a limit of 5% of the contract sum. Your own contract sets your own figures.

The retention limit is 5% × S$180,000.00 = S$9,000.00.

Progress claim 3 covers work done up to 30 Nov 2026.

Contract itemItem valueDone to dateWork done to date
A. Containment and cablingS$80,000.0060%S$48,000.00
B. Lighting and power pointsS$60,000.0040%S$24,000.00
C. Distribution boardsS$40,000.0025%S$10,000.00
Contract work done to dateS$180,000.00S$82,000.00
Approved variation S-VO-01S$3,000.00100%S$3,000.00
Total work done to dateS$85,000.00

The desk would then work out the claim.

StepArithmeticAmount
Total work done to dateS$82,000.00 + S$3,000.00S$85,000.00
Retention to date10% × S$85,000.00 = S$8,500.00, which is below the S$9,000.00 limitS$8,500.00
Net amount to dateS$85,000.00 − S$8,500.00S$76,500.00
Less the net amount of claims 1 and 2S$50,000.00 − S$5,000.00S$45,000.00
Amount of progress claim 3S$76,500.00 − S$45,000.00S$31,500.00

A second check gives the same answer. The work done in this period is S$85,000.00 − S$50,000.00 = S$35,000.00. The retention in this period is S$8,500.00 − S$5,000.00 = S$3,500.00. S$35,000.00 − S$3,500.00 = S$31,500.00.

When the retention reaches its limit

Suppose that the total work done reaches S$100,000.00 at progress claim 4. Then 10% × S$100,000.00 = S$10,000.00, which is above the S$9,000.00 limit. The retention to date is S$9,000.00, and the retention in that period is S$9,000.00 − S$8,500.00 = S$500.00.

A spreadsheet that takes 10% of every claim would hold back S$1,500.00 in that period. That is S$1,000.00 too much. A desk would apply the limit in each claim, with the arithmetic in view.

The person still sets the percentage done for each item and still signs the claim.

The site DO log: one worked line

Sample data. Supplier G (sample) delivers cable tray to the site of Customer B (sample) on 12 Nov 2026.

FieldValue
Delivery orderS-DO-7101
Contract itemA. Containment and cabling
Quantity on the DO120 lengths
Quantity accepted on site118 lengths. 2 lengths were damaged and went back.
Signed bySite supervisor of Example M&E Works (sample company)
Supplier invoice S-INV-7108Bills 120 lengths at S$22.00 = S$2,640.00
Accepted value118 × S$22.00 = S$2,596.00
Difference2 × S$22.00 = S$44.00

A desk for the site DO log would show that the supplier invoice bills 2 lengths more than the site accepted. A person asks the supplier about the S$44.00.

What changes and what does not

TopicWhat stays the sameWhat changes
Your claim formatThe desk keeps your own Excel claim layout where you want that. A customer that needs its own form still gets that form.The cumulative figures come from one record, not from last month's file.
Site photos and chat groupsSite staff can keep the same chat groups, if you want that.A person enters each DO in the desk once. The chat is not the record.
Paper DOThe site signs the paper DO, as it does today.The desk records the DO number, the accepted quantity and where the paper is.
Accounting softwareYour accounting software stays.Nothing changes there, unless the written scope names an export layout.
DecisionsA person sets the percentage done, claims and follows up.A person decides from one list, not from memory.

Data and privacy

Your dataYour data stays private to your company.
First conversationThe first conversation needs no confidential files.
Outside AI servicesBefore any outside AI service reads a file, WorkflowLab asks whether the file is under an NDA.
AI readingsWhere AI reads documents, a person can check every reading against the source.
AI in the deskA desk does not need AI. A claim is arithmetic and plain rules.

What a desk does not do

AI reads. Plain rules decide. People approve.

  • A desk does not value the work. A person sets the percentage done for each item.
  • A desk does not send a claim, and it does not approve anything.
  • A desk does not give contract advice or legal advice. It does not decide a date or a right under your contract or under the law on construction payments.
  • A desk does not release payments, and it does not collect payments.
  • A desk covers one job. It is not project management software and it is not a full business system.

The retention figures in this guide are sample figures. Your contract sets the rate, the limit and the release dates. Ask your contract adviser if you are not sure.

Packaged construction software covers many jobs in one product. It can be the better choice for a company with many departments. The guide Custom Ops Desk vs SaaS vs ERP compares the 3 choices.

Price, delivery and the walkthrough

There is no public price list for Custom Ops Desks. After the workflow walkthrough, you get one written scope with one fixed price. Work starts only after you accept the scope.

We plan the first useful result within 1 week of the day we receive your sample files. After handover, you run the desk alone, or the first quote names a small monthly support fee.

A desk that includes an AI system may qualify for the Singapore 400% tax deduction for AI spending. Your accountant confirms what qualifies, and the EIS guide gives the rules.

What to prepare for the workflow walkthrough

Each walkthrough session is at most 30 minutes, on your schedule.

  • Name the 1 job that costs most, and who does it.
  • Count your live contracts and the claims in 1 normal month.
  • Bring 1 blank copy of your claim spreadsheet, without the customer data.
  • Bring 1 blank site DO.
  • Choose 1 finished claim that you can follow from the site to the payment.
  • Note which files are under an NDA.

To see the kind of desk WorkflowLab builds, open the equipment rental, billing and maintenance desk. It uses sample data only.

WhatsApp and Excel are trademarks of their owners. WorkflowLab is not affiliated with or endorsed by them.

Questions about a desk for a subcontractor

What progress claim software fits a small subcontractor in Singapore?

Packaged construction software covers many jobs and fits a company that can configure and learn a full system. A Custom Ops Desk is one private browser page or one Excel workbook for one job. It fits a company with fewer than 10 office staff where 1 person builds every claim.

How do we work out a progress claim with retention?

Add the work done to date for each contract item and each approved variation. Subtract the retention to date, up to its limit. Then subtract the net amount of the earlier claims. In the sample in this guide, S$85,000.00 − S$8,500.00 − S$45,000.00 = S$31,500.00.

How do we track retention sums across several contracts?

Keep one line for each contract: the retention that the customer holds, the limit, and the dates when your contract says it is due. A desk for this job would hold that list and show what is due. A person asks for the release.

Can a desk keep our own claim format?

Yes, where you want that. The desk keeps your own Excel claim layout. A customer that needs its own form still gets that form. The written scope names each layout.

Does a desk tell us when a payment claim is due under the law?

No. A desk can show a date that a person enters from the contract. It does not decide a date or a right, and it gives no legal advice.

How much does a desk for a small subcontractor cost?

There is no public price list. After the workflow walkthrough, you get one written scope with one fixed price. Work starts only after you accept the scope.

Describe the job your team does every week.

Send a short email. Name the job, who does it, and what you use today. The first conversation needs no confidential files.

Every demo runs in your browser with sample data. A Custom Ops Desk has no public price list. You get one written scope with one fixed price before any build starts.